What do “The Last Jedi” and Georgia actually have in common?

At the end of December, just when everyone was focused on the premier of the new Star Wars movie “The Last Jedi” (and the holiday season), the Georgia Public Service Commission ignored their own Staff’s recommendations – and that of intervenors including the Southern Alliance for Clean Energy – and unanimously voted to allow the [...]

Energy Storage: Charging Ahead in 2018

Duke Florida plans to add 50 MW of battery storage.
Kentucky Power’s IRP has plans for adding 10 MW of battery storage by 2025.
Duke Energy in North Carolina will install a 9 MW battery system in transmission-constrained Asheville.
West Virginia’s Laurel Mountain wind farm has a co-located 32 MW / 8 MWh lithium-ion battery system.
Duke Energy’s Notrees Windpower Project in western Texas is upgrading from lead-acid batteries to a 36 MW lithium-ion system.
Southern Company is testing a 1 MW / 2 MWh lithium-ion battery system in Cedartown, Georgia.
Southern Company and Gulf Power are testing a 250 kW / 1 MWh Tesla Powerpack in Pensacola, Florida.
Chattanooga, Tennessee’s Electric Power Board (EPB) has energized a 100kW/400kWh Vanadium flow battery.
Entergy New Orleans paired its new 1 MW solar PV facility with a 500 kWh lithium-ion battery system.
Arkansas Electric Cooperative Company began evaluating battery storage in 2015 for its IRP.
Dominion Energy (Virginia) has an IRP that evaluates battery storage, and even pumped-hydro storage.

Will Plant Vogtle Nuke Georgia Power Bills? Act Now!

This has been an intense week for the Plant Vogtle nuclear expansion project so here’s a quick blog to get you updated. SACE has been on the ground at the public hearings all week where we learned that Georgia’s Public Service Commissioners have expedited their timeline to make a decision on Georgia Power’s request to double the estimated costs for Plant Vogtle by Dec 21st, not February 2018, like originally scheduled! Georgia Power is asking to push those costs onto YOU, instead of its shareholders. With less time to flood the inboxes of the Commissioners, we really need your help!

Are industrial power customers favored too much?

Across the Southeast, industrial power customers get special perks. One reason is that they can afford to hire lawyers and experts to persist in asking for the most favorable treatment they can get. One example of this is the advance payment for Georgia Power Company’s Plant Vogtle nuclear expansion project. Georgia Power customers have already [...]

Energy efficiency is trending up and down in the Southeast

Yesterday we reported on how Duke Energy leads the Southeast in energy efficiency, and Florida Power & Light is providing the worst results in the region. But what about the rest? There are a lot of great stories to tell, but first here’s a reminder of the overview. We report on the recent performance of [...]

Duke Energy leads the Southeast on energy efficiency

Duke Energy Carolinas has reached the 1% energy savings benchmark in 2016, a nationally recognized indicator of success in providing customers with energy efficiency programs. Congratulations to all the staff at Duke Energy for that achievement! Since we last reported utility energy efficiency savings in 2014, we have seen some remarkably good as well as [...]

New Analysis Begs The Question: Is Vogtle Project Too Costly To Complete?

In advance of the Thursday, June 29, 2017 hearing on the 16th semi-annual Vogtle Construction Monitoring (VCM) review before the Georgia Public Service Commission, we wanted to share this timely guest blog. Please attend the hearing if you can and voice your concerns to the Commissioners. If you cannot, please sign this petition demanding consumer [...]

Setting the Bar for Energy Efficiency Programs in the Southeast

The American Council for an Energy Efficient Economy (ACEEE) released its 2017 Utility Energy Efficiency Scorecard yesterday, ranking the 51 largest US electric utilities on energy efficiency programs and policies in 2015. Utility efficiency programs can have a number of benefits including lowering customer bills, reducing or avoiding the need to build new generating plants and other societal benefits like improved health and job creation. How did the utilities in the Southeast utilities perform on the scorecard? Let’s take a look.

Pruitt EPA Should Deny New Utility Move to Weaken Federal Coal Ash Rule

Like last month’s stay on the water discharge rule, a potential stay on the Coal Ash Rule extends unconscionable risk for the people who live near coal ash pits, which can rupture or leak toxics into drinking water, while pandering to corporate utilities that have gotten away with dangerous waste handling for decades.

Not one more cent! Georgia Power customers irate over Vogtle nuclear mess

Last Thursday the Georgia Public Service Commission (PSC) held the first hearing in the 16th semi-annual Vogtle Construction Monitoring (VCM) review, so that Georgia Power could ask for approval for $222 million in expenditures spent during the July 1 to December 31, 2016 period for their two delayed, over budget Toshiba-Westinghouse AP1000 reactors under construction [...]